1、
Being assigned as the project manager to a project
2、
The type of contract where the buyer incurs opport
3、
Cost of quality is the total cost of all efforts t
4、
A particular stakeholder has a reputation for maki
5、
In your software development project you have to w
6、
Your project is executed with a globally spread vi
7、
Out of the following definitions of a project stak
8、
The method of constructing a project schedule netw
9、
Earned value technique is used in which process ?(
10、
The following are the internal rate of return(IRR)
11、
During the execution phase of project,you realize
12、
All of the following are parts of an effective cha
13、
Which of the following describes the BEST use of h
14、
While working on an external project your customer
15、
The high-level project schedule constraints have j
16、
Executing processes are concerned with ().
17、
At the end of the closing process group,().
18、
In a project status meeting,you identified that a
19、
The project sponsor has just provided the project
20、
All of the following must be performed during proj
21、
A team member notifies the project manager that th
22、
A review of management processes and the associate
23、
Which of the following is NOT an input to the init
24、
Which of the following documents is not used as in
25、
The person who should be in control of the project
26、
Which of the following is the most common non-beha
27、
In a recent job interview,you were asked to define
28、
All of the following are parts of direct and manag
29、
As a project manager,you advocate active participa
30、
A project management team has subcontracted work t
31、
Which of the following is not an example of constr
32、
Companies and institutions most commonly hire proj
33、
The WBS,estimates for each work package,and the ne
34、
A project management team is evaluating the causes
35、
What is the purpose of a project charter ?()
36、
You are the project manager responsible for develo
37、
Major difficulties arise when multiple projects ne
38、
A customer informed you that it is preferable to c
39、
Which of the following is true regarding estimatio
40、
The project manager has just received a change fro
41、
All the following statements are true except:().
42、
A project manager recently rewarded an individual
43、
Which of the following is not a tool of the activi
44、
Which of the following establishes quality metrics
45、
What is not a reason for companies to organize les
46、
Which of the following is not a project management
47、
A project manager is managing a fixed price(FP)con
48、
A project has the following earned value data asse
49、
In an object diagram.the name of an object is ().
50、
You are a new project manager who has never manage
51、
As per PMBOK,all are parts of the executing proces
52、
Which of the following is not a tool & technique o
53、
During activity sequencing,you identify and docume
54、
To manage a project including ().
55、
You are assigned as the project manager in a proje
56、
() is typically not referred to as a buffer type i
57、
When deciding which project to select,().
58、
Which of the following statements is not true ?()
59、
In a traditionally drawn decision tree,a circle re
60、
Which of the following indicates the acceptable ra
61、
A project management team wants to procure some cu
62、
During project execution,the customer authorizes a
63、
The project is not completed until ().
64、
When there are conflict in the contract,() is the
65、
The close project process is a part of which of th
66、
When the project cost is $2000 and the profit is $
67、
In which of the following organizational structure
68、
Why is it important to have a project charter ?()
69、
Request seller responses and select sellers is ass
70、
If CPI is 1.03 and AC is 6000,how much is EV ?()
71、
Which of the following process is not Fart of proj
72、
In which type of organization is the project manag
73、
Who has the highest cost risk in case of a fixed p
74、
A detailed project schedule can be created only af
75、
What is true when a change control system's provis
76、
Which of the following is not used in the quality
77、
An organization structure that involves various or
78、
In your project,you use the“develop project team”p
79、
In your project,you want to monitor and control pr
80、
The knowledge area that describes the processes an
81、
When should lessons learned be organized ?()
82、
You have been working on a very large software dev
83、
A procurement audit is a structured review of the
84、
Calculate the standard deviation of a task if O=4,
85、
Which of the following is the best use of lessons
86、
You are in the close project process.You are engag
87、
The concept of the () states that changes related
88、
A work authorization system can be used to ().
89、
A project manager does not have much time to spend
90、
In managing a project,you notice that a deliverabl
91、
Who is responsible for completing the lessons lear
92、
What is done after a feasibility study ?()
93、
A project manager is at the project kick-off meeti
94、
Integration is done by the ().
95、
Which of the following is NOT an input to monitor
96、
If SV=800,PV=7000,how much is EV ?()
97、
A complex project will fit best in what type of or
98、
A project manager has just been assigned to a new
99、
Company procedures require the creation of a lesso
100、
A paint manufacturer authorizing a project to esta
101、
Even though you are a project manager in a pharmac
102、
The project charter for a project was approved for
103、
Which of the following BEST describes a project ma
104、
Which of the following statements is NOT true rega
105、
You have recently appointed a project manager to h
106、
A manufacturing project has a schedule performance
107、
Who is responsible for quality management in the p
108、
Which knowledge area does the develop project char
109、
Which of the following statements regarding whistl
110、
All technical work is completed on the project.Whi
111、
In your software development project you have plan
112、
The project manager is making sure that the produc
113、
The project charter is created in which project ma
114、
While doing quality inspection,few defects were id
115、
The project team has just completed the initial pr
116、
Which of the following activities is not concerned
117、
For an activity,the optimistic,most likely and pes
118、
Which of the following BEST describes the verify s
119、
As per PMBOK,various executing processes fall into
120、
All of the following would occur during the closur
121、
A project manager learns that corrective action wa
122、
Which type of input is the primary cause of contra
123、
You are managing a project in a foreign country,wh
124、
You are assigned as the project manager in the mid
125、
You are the project manager of a new project,which
126、
What is the process for aggregating the estimated
127、
Which of the following is NOT a method for progres
128、
Which of the following are the most commonly used
129、
Which of the following process involves determinin
130、
The client demands changes to the product specific
131、
During a project the scope of a product purchased
132、
A project management plan should be realistic in o
133、
As a project manager,project plan development is a
134、
which of the following is the BEST tool for showin
135、
At the beginning of project execution,you notice d
136、
Which type of warranty is enacted if a service or
137、
In which phase of the project life cycle,are cost
138、
Being the project manager in a software project wh
139、
How should change management be planned for ?()
140、
Understanding of () characteristics of people is n
141、
You are the project manager of Alpha Network Inc.Y
142、
You do not expect the types of variances that have
143、
What does the acronym RACI commonly stand for in p
144、
An output of close project is the creation of ().
145、
Based on the net present value(NPV),which project
146、
Which of the following is included in a project ch
147、
In case of conflicts of interest among stakeholder
148、
Which of the following is a common characteristic
149、
Requirements documentation is an input to ().
150、
The following information is available about a par