In your project,you use the“develop project team”process to improve the competencies and interaction of team members to enhance project performance.
The outputs from this process are ().
A:project staff assignments B:team performance assessment C:staffing management plan D:project staff assignments,staffing management plan,team performance assessment
Management of the project team is complicated ______ .
A:when team members are co-located B:when minor problems do not impact the project completion date OE budget target C:when team members are accountable to both a functional manager and the project manager D:when formal training plans are implemented
Which of the following factors contributes the most to team communication
A:External feedbac B:Performance appraisal C:Smoothing over of team conflicts by the project manage D:Collocatio
Team-building activities include management and individual actions taken I specifically and primarily to improve team performance. Many of these actions may enhance team performance as a secondary effect. An example of some action that may enhance team performance as a secondary effect is ______ .
A:establishing team performance goals and holding off-site retreats to review ways of best achieving these goals B:collocating all teams members in a single physical location C:establishing a team-based reward and recognition system D:involving non-management-level team members in the planning process
In your project,you use the“develop project team”process to improve the competencies and interaction of team members to enhance project performance. The outputs from this process are ().
A:project staff assignments B:team performance assessment C:staffing management plan D:project staff assignments,staffing management plan,team performance assessment
______ is the process of improving competencies, team member interaction, and overall team environment to enhance project performance.
A:Develop Project Team B:Manage Project Team C:Plan Human Resource Management D:Acquire Project Team