Rebaselining may be required in cost control when ().
题库:PMP项目管理师考试
类型:最佳选择题
时间:2017-07-02 16:30:51
免费下载:《单选题》Word试卷
Rebaselining may be required in cost control when ().
A.CVs are severe, and a realistic measure of performance is needed
B.revised cost estimates are prepared and distributed to stakeholders
C.corrective action must be taken to bring expected future performance in line with the project plan
D.EAC shows that additional funds are needed to complete the project even if a scope change is not needed