Which of the following is not a project management knowledge area
A:Project integration management. B:Project procurement management. C:Project configuration management. D:Project communications management.
The knowledge area that describes the processes and activities that integrate the various elements of project management is ().
A:project scope management B:project time management C:project integration management D:project communication management
Project integration management includes the processes and activities needed to identify, define, combine, unify and coordinate the various processes and project management activities. For successful project integration management, you should definitely have () (select the best option).
A:a strong matrix organizational structure in your company B:a good communication management plan C:good project selection techniques D:positive stakeholders who support the project
How should change management be planned for ?()
A:Changes are generally not predictable, therefore planning for change management cannot be sensible B:Planning for change management should be done while the various change control processes are being applied C:Change management can be planned in a set of management plans or a specific change management plan D:Changes are a sign of bad planning. One should avoid changes during a project thus eliminating the need to manage them
Project management techniques applied to ongoing operations is called as ().
A:portfolio management B:management by projects C:management by objectives D:management by exception
The knowledge area that describes the processes and activities that integrate the various elements of project management is ().
A:project scope management B:project time management C:project integration management D:project communication management
How should change management be planned for ?()
A:Changes are generally not predictable,therefore planning for change management cannot be sensibl B:Planning for change management should be done while the various change control processes are being applie C:Change management can be planned in a set of management plans or a specific change management pla D:Changes are a sign of bad planninOne should avoid changes during a project thus eliminating the need to manage the
Project integration management includes the processes and activities needed to identify,define,combine,unify and coordinate the various processes and project management activities.For successful project integration management,you should definitely have () (select the best option).
A:a strong matrix organizational structure in your company B:a good communication management plan C:good project selection techniques D:positive stakeholders who support the project
Quality management()
A:is another name for careful inspections B:is inversely related to productivity C:is primarily the responsibility of management D:is primarily the responsibility of the workers