If Task B has 15 days of free float and 25 days of total float, and the early start date of Task B is delayed 30 days, how is the project affected
A:The next dependent task's start date will be delayed 15 days. B:The duration of the task will be shortened 15 days. C:The completion date of the project will be pushed out 5 days. D:Both A and C.
If Task C has 0 days of free float and 0 days of total float, what does this mean to the project
A:The project does not have adequate lead and lag times built in. B:The task is on the critical path. C:The duration of the task should be compressed. D:The dates for the task are not accurate.
The following information is available about a particular task in your project plan:early start(ES), 25 days;late start(LS), 30 days;early finish(EF), 50 days;late finish(LF), 55 days. Based on this information。you can deduce that()
A: the project float is 5 days B:the project may get delayed C:the task is not on the critical path D:the task is on the critical path
Task A has the following details:Optimistic estimate=30, pessimistic estimate=40, most likely estimate=35. Task B has the following details:Optimistic estimate=32, pessimistic estimate=37, most likely estimate=34. Task C has the following details:Optimistic estimate=25, most likely estimate=35, pessimistic estimate=45. Which task has the highest standard deviation ()
A: Task B:Task C:Task D:Task A & Task
The following information is available about a particular task in your project plan:early start(ES), 25 days;late start(LS), 30 days;early finish(EF), 50 days;late finish(LF), 55 days. Based on this information。you can deduce that ().
A:the project float is 5 days B:the project may get delayed C:the task is not on the critical path D:the task is on the critical path
You have been given a high priority task that needs to be completed within a short time frame.Since you know what has to be done,you assign tasks to the different team members and tell them when and how the tasks should be done.The management style that you are following is ().
A:directing B:laissez faire C:delegating D:task-oriented
The following information is available about a particular task in your project plan:early start(ES),25 days;late start(LS),30 days;early finish(EF),50 days;late finish(LF),55 days.Based on this information。you can deduce that ().
A:the project float is 5 days B:the project may get delayed C:the task is not on the critical path D:the task is on the critical path
Task A has the following details:Optimistic estimate=30,pessimistic estimate=40,most likely estimate=35.Task B has the following details:Optimistic estimate=32,pessimistic estimate=37,most likely estimate=34.Task C has the following details:Optimistic estimate=25,most likely estimate=35,pessimistic estimate=45.Which task has the highest standard deviation ?()
A:Task B:Task C:Task D:Task A & Task
You have been given a high priority task that needs to be completed within a short time frame.Since you know what has to be done,you assign tasks to the different team members and tell them when and how the tasks should be done.The management style that you are following is ().
A:directing B:laissez faire C:delegating D:task-oriented
Something Men Do Not Like to Do
Eric Brown hates shopping. “It’s just not enjoyable to me,”said the 28-year-old Chicago man who was carrying several shopping bags along the city’s main street,Michigan Avenue.“When I’m out______(51),I basically know what 1 want to get. I rush in.I buy it.I______(52).”
Common wisdom says that guys hate to shop.You can ask generations of men. But people who study shopping say that a number of social,cultural and economic factors are now______(53) this “men-hate-to-shop” notion.
“______(54)social class and age,men say they hate to shop,”says Sharon Zukin,a City University of New York sociology professor.“Yet when you ask them deeper questions, it turns out that they_____(55)to shop.Men generally like to shop for______(56),music and hardware(硬件).But if you ask them about the shopping they do for books or music,they’ll say,“Well,that’s not shopping.That’s_____(57).”
In other words,what men and women call “buying things”and how they approach that task are______(58).Women will______(59)through several 1,000-square-metre stores in search of the perfect party dress.Men will wander through 100 Internet sites in search of the______(60)digital camcorder(摄像放像机).Women see shopping as a social event.Men see it as a mission or a______(61)to be won.
“Men are frequently shopping to win,”says Mary Ann McGrath,a marketing professor at Loyola University of Chicago.“They want to get the best deal.They want to get the best one,the Last one and if they do that it_____(62)them happy.”
When women shop,“they’re doing it in a way where they want_____(63)to be very happy,”says McGrath.“They’re kind of shopping for love.”
In fact,it is in clothing where we see a male-female______(64)most clearly.Why, complain some men,are all male clothes navy, black or brown? But would they wear light green and pink(粉红色的)?These days,many guys wear a sort of“uniform”,says Paco Underhill,author of“Why We Buy”.“It’s been hard for them to understand what it means to be fashion-conscious(时尚意识)in a business way.It becomes much,much easier______(65)you narrow your range of choices.”
A:task B:play C:game D:destination