Estimate at completion(EAC) is ______.

A:actual cost(A+budgeted cost(B B:actual cost(A+estimate to complete(ET C:budgeted cost(B-actual cost(A D:actual cost(A-planned value(PV)

What is the purpose of the contingency money in a cost estimate ?()

A:Provides money to cover uncertainties in the estimate within the defined scope and schedule B:Money to cover changes in scope C:Money to cover unforeseen natural disasters D:A and C

Estimate at completion(EAC) is ().

A:actual cost(AC)+budgeted cost(BC) B:actual cost(AC)+estimate to complete(ETC) C:budgeted cost(BC)-actual cost(AC) D:actual cost(AC)-planned value(PV)

While reviewing the estimates from the functional managers assigned to your project you discover that one cost estimate is clearly higher than those submitted for previous projects. You should ______ .

A:reject the estimate and remove the functional manager from the project B:request the supporting details for the estimate to ensure it has been properly prepared C:accept the estimate and plan to use the additional funding as a reserve D:question each functional manager for information about this estimate

The estimate is ().

A:actual cost (AC) + budget cost (BC) B:the actual cost (AC) + completion is still needed to estimate (ETC) C:budget cost (BC) - actual cost (AC) D:actual cost (AC) - planned value (PV)

The Estimate Activity Resource process is closely coordinated with the (73) process.

A:Estimate Costs B:Sequence Activities C:Plan Communications D:Conduct Procurements

The Estimate Activity Resource process is closely coordinated with the (73)process.

A:Estimate Costs B:Sequence Activities C:Plan Communications D:Conduct Procurements

The Estimate Activity Resource process is closely coordinated with the ______ process.

A:Estimate Costs B:Sequence Activities C:Plan Communications D:Conduct Procurements

The Estimate Activity Resource process is closely coordinated with the ______ process.

A:Estimate Costs B:Sequence Activities C:Plan Communications D:Conduct Procurements

微信扫码获取答案解析
下载APP查看答案解析