Which of the following establishes quality metrics ?()

A:Quality assurance & Quality control. B:Quality planning. C:Quality baseline. D:Quality checklist.

An outputs from the quality planning process is ______ .

A:quality improvements B:quality management plan C:acceptance decisions D:rework

In quality planning:

A:The primary benefit of meeting quality requirements is the reduced expense associated with project quality management activities. B:Cost-benefits tradeoffs must be considered. C:The primary cost of meeting quality requirements is increased rework. D:Benefits cannot be evaluated in relation to costs.

Which of the following establishes quality metrics ?()

A:Quality assurance & Quality contro B:Quality plannin C:Quality baselin D:Quality checklis

In quality planning:

A:The primary benefit of meeting quality requirements is the reduced expense associated with project quality management activitie B:Cost-benefits tradeoffs must be considere C:The primary cost of meeting quality requirements is increased rewor D:Benefits cannot be evaluated in relation to cost

Which of the following is not part of the quality assurance process ______

A:Operational definitions B:Quality policy C:Quality audits D:Quality improvement

Which of the following is not part of the quality assurance process ().

A:Operational definitions B:Quality policy C:Quality audits D:Quality improvement

Which of the following is not part of the quality assurance process ( )

A:Operational definitions B:Quality policy C:Quality audits D:Quality improvement