When should a project baseline be changed

A:When a major delay occurs. B:When an official change is made. C:When a cost increase occurs. D:Changes should never be made in the baseline.

When should the project baseline be changed

A:It should not he changed. B:Only for changes that have been approved by the change control board. C:At each project team meeting. D:For all implemented changes.