If a project manager communicates a verbal message to a subordinate and the subordinate leaves without saying a word,the project manager should assume that______.
题库:PMP项目管理师考试
类型:最佳选择题
时间:2017-07-02 16:30:52
免费下载:《单选题》Word试卷
If a project manager communicates a verbal message to a subordinate and the subordinate leaves without saying a word,the project manager should assume that______.
A.the message was understood
B.the message was not understood
C.the message may not have been understood
D.the information was not appropriate