()is the management system to control the material consumed, reduce inventory in the manufacture company.
A:DRP (Distribution Resource Planning) B:LRP (Logistics Resource Planning) C:MRP (Material Requirements Planning) D:ERP (Enterprise Resource Planning)
A management control point can be placed at selected management points (specific components at selected levels)of the WBS above. the work package level. These control points can be ______ .
A:used for rolling wave planning B:decomposed further to help in creation of work authorization system C:used for planning known work content that does not have detailed schedule activities D:used as a basis for planning when associated work packages have not yet been planned
You have been assigned to manage a large enterprise resource planning(ERP) project in your organization.You realize that detailed planning,execution,and closing processes are prerequisites for success.To support the project from initiation through closing you should use ().
A:a make-or-buy analysis B:lessons learned and other historical information from previous projects C:benefit-cost analysis D:the project management information system
The author suggests that energy savings could be realized______
A:with more effective transportation of consumer goods B:with better educational programs and planning techniques C:with an efficient system of inner-city transportation D:with forceful limitation of the use of the automobile
Most system development methodologies also provide (71) , whose purpose is to contain the various pieces of relevant information-feasibility assessments, schedules, needs analysis, and so forth-in a single place so that they can be presented to project clients and other related parties.
A:statement of work B:project planning C:baseline plan D:information system planning
An Enterprise Resource Planning (ERP) is built upon a commercial()that promises the seamless ()of all the information flowing through the company ─financial, accounting, human resources, supply chain and customer information. In implementation, all ERP systems include several features. The system is installed on a typical database management system. It requires initial setup according to the organization’s process, but it may be()according to the organization’s unique process requirements through a tool set contained within the ERP applications. Using ERP,()can be prescribed to automate approval processes through established chains of command. One of the methods used to effect rapid implementation of the ERP system is to conduct concurrent()sessions during the early stages of ERP implementation.
An Enterprise Resource Planning (ERP) is built upon a commercial()
A:operating system B:middleware C:software package D:management system
Accelerated analysis approaches emphasize the construction of () to more rapidly identify business and user requirements for a new system. As an accelerated analysis technology,() reads the program code and automatically generates the equivalent system model, and the code can be obtained from () . All system analysis approaches require some form of () which includes those techniques to be used to identify or extract system problems and solution requirements from user community. () is a classical set of techniques used to collect information about system problems, opportunities, solution requirements, and priorities.
()is a classical set of techniques used to collect information about system problems
A:Continuous process improvement B:Joint requirements planning C:Fact-finding D:Structured engineering